A contract on construction job specifies a penalty for delay in completion of the work beyond a certain date is as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day etc., the penalty for each succeeding day being Rs. 50 more than that of the preceding day. How much penalty should the contractor pay if he delays the work by 10 days?
Correct Answer: (B) Rs. 4250
Correct Answer: (B) Rs. 4250
Detailed Step-by-Step Analysis:
In UPSC CSE Prelims 2011 CSAT (GS Paper-II, Question 35), the officially verified answer is Option (B): "Rs. 4250". This question tests Basic Numeracy (Quantitative Aptitude).
Option Verification & Elimination:
Evaluating the problem constraints confirms (B) "Rs. 4250" as the unique valid solution, eliminating (A) Rs. 4950; (C) Rs. 3600; (D) Rs. 650.
CSAT Approach & Exam Strategy:
• Section & Topic: CSAT Paper-II › Basic Numeracy › Quantitative Aptitude.
• How to Solve Faster: Translate the word problem into clean algebraic equations or test boundary values/ratios directly from the options. Watch for divisibility rules, unit-digit cyclicity, percentage-to-fraction shortcuts, and integer constraints.